2026 Technical Guide

Storing Polyethylene Pipe: Transport and Delivery Inspection

Ertunç Plastik Technical Content Team5 min reading

When receiving the polyethylene pipe, first compare the product print with the order; Then check the packaging, body and crushing. Prepare a flat and clean storage area; Determine the transport and stacking arrangement in accordance with the manufacturer's instructions.

Do not just count the number of rolls when receiving

Compare colour, diameter, pressure class and requested quantity with the delivery note and product printing. Do not use appearance alone as identification as there may be different sizes or grades in the same colour.

Record any damage to the packaging and any visible dents or cuts upon delivery. Separate the suspicious product from healthy products and report it to the seller. The safe use limit of the damage cannot be determined by photography alone.

Prepare the floor and storage location

PPI recommends a smooth storage surface, free of stones and debris that could damage the pipe. The coil must be prevented from rolling or tipping over. The layout must comply with the product and packaging instructions.

Separate the warehouse from the passage of work machines. Dragging on the ground, hard edges and uncontrolled loads can damage the hull. Having free space alone does not mean that a safe stack can be established.

Do not mix products 6, 10 and 16 ATÜ

Use separate, readable product fields by diameter and pressure class. Instead of just writing “blue pipe” on the label, record the actual product name, diameter, class and batch information.

Black–yellow line or blue–orange line makes color description easy when ordering; PE class alone is not a drinking water suitability or pressure certificate. Product printing and verified technical information must be taken as basis.

Control the Coil Before Cutting Its Ties

Unexpected movement may occur when unwrapping the polyethylene pipe. The process of cutting and opening ties requires appropriate equipment, space, and manufacturer procedure. Do not perform any operations until the coil is fixed and the work area is secured.

Do not try to carry heavy rolls manually by estimating the number of people. The weight of the load, lifting equipment and handling points of the packaging must be evaluated by competent persons. This guide is not a removal or field safety project.

How long can it be stored outdoors?

There is no universal outdoor storage period for all PE pipes. Material, stabilisation, packaging and the manufacturer's declaration differ. Do not apply another brand's UV data to an Ertunç Plastik product to estimate a storage period.

Record the beginning of storage and ask for the product's own instructions. Take into account that surfaces exposed to sunlight may become hot and wet pipes may be slippery. Do not heat straighten or flame.

Final check before shipping to the field

Separating products according to application stages reduces the risk of opening the wrong roll. Double check the metering, diameter and class; Don't lose definition of remaining rolls.

Specify the access and unloading conditions of the delivery location in the offer. Verify in writing what services the shipping cost includes; Do not assume that delivery automatically includes crane or unloading labor.

Frequently Asked Questions

Can polyethylene pipes be stacked?

Only in the stacking order permitted by the manufacturer and packaging. A valid coefficient number cannot be given for every diameter.

Does polyethylene pipe deteriorate in the sun?

Outdoor suitability depends on product material and verified stabilization information; However, duration cannot be subtracted from color.

Can the blue pipe and the black pipe be placed in the same place?

Safe storage conditions must be ensured; Products must be identified separately with diameter, class and identity information.

Does the line color indicate class ATÜ?

It doesn't show on its own. Printing, labeling and verified product registration are checked together.

Should pipe-coil straps be cut on delivery?

It should not be cut uncontrolled. Opening is carried out according to the manufacturer's procedure and secure fixing.

Can the pipe be carried by dragging it on the ground?

Avoid dragging which could damage the hull; Use appropriate handling method and equipment.

Can a crushed pipe be fixed by heating?

Do not apply heat or flame on your own. Report the damage to the manufacturer and seek appropriate evaluation.

How to separate 6 and 10 ATÜ in the warehouse?

Separate into separate labeled fields with diameter, grade and batch information; Don't rely on the color code alone.

Is unloading included in the shipping price?

It depends on the scope of offer. Clarify equipment, labor and access conditions in writing before ordering.

How to report storage damage?

Share the photo of product printing, packaging and damaged area with the order information; Disconnect the suspect product from use.

Let's determine the appropriate product and size together

Write the diameter, length, area of use and delivery city; Request a quote with up-to-date product information.